In compliance with DOT 49 CFR 178.2 (c), persons shipping Skolnik drums must comply with the following closure instructions. Failure to do so will invalidate the UN and 7A ratings of Skolnik drums. Use of components other than those supplied with the drum (or identical replacement parts from Skolnik) will also invalidate the UN rating.
Important: Please contact Skolnik Industries for further instructions if encountered with difficulties in meeting these requirements. Do not ship the drum.
Open Head Drum - Bolt Ring Closure
- Check Gasket: Ensure that the gasket is properly fitted in the cover groove. (Fig. 1 or 2)
- Place Cover on Drum Curl: (Fig. 3) Be careful to properly seat gasket around curl.
- Position & Seat Ring — with lugs downward. Ensure the inner channel of the closure ring engages entire drum curl and cover (Fig. 4). Apply downward pressure on cover, use a rubber mallet to hammer ring to further seat ring, cover & drum curl into inner channel of ring.
- Install Bolt: Insert bolt through unthreaded lug, screw bolt into locking nut, then into threaded lug (Fig. 5).
- Close Drum: Tighten bolt (using downward pressure on the cover and hammering outside of ring with a rubber mallet will assist closing process). Continue tightening and hammering ring until the ends of the ring reaches the maximum gap shown in the chart below. NOTE: Ring ends should not touch and ring must be in a fixed position. The lock nut must be tightened against the un-threaded lug. (Fig. 6)
Performance Note: Ring gap compliance is critical for the performance of Skolnik drums. Closure is assured by compressing the cover and gasket to the drum body. This is achieved when the final tightened ring gap (therefore final ring diameter) meets the specifications listed.
Ring Gap Requirements
| Drum Size |
U.N. Markings |
Max Gap |
| 5-16 Gal. |
liquid & solid |
0.500" (12.70 mm) |
| 20-110 Gal. |
liquid & solid |
0.125" (3.175 mm) |
| 5-110 Gal. |
solids only |
1.0" (24.4 mm) |
| 55 Gal Composite |
liquid |
0.850" (21.59 mm) |
55 Gal 7A rating |
solids only |
Option A: close to 1" gap, then torque to 25 ft-lbs Option B: close to .125" gap |
Important: If ring ends touch when closed to instructions please contact
customer service for further instruction. Do not ship the drum.

Open Head Drum - Leverlock Closure
- Check Gasket: Ensure gasket is properly fitted into cover groove.
- Place Cover on Drum: (Fig. 3) being careful to properly seat gasket around curl.
- Open Leverlock: Place expanded ring on to the drum cover with the vertical-skirt hugging the drum body.
- Close Leverlock: Slowly and cautiously close the LEVERLOCK so that the outer ring engages the cover / body juncture. Downward pressure along with tapping the outside of the ring may assist in an even closure
- Engage Lock: Engage latch to lock into place.
 |  |
| Expanded ring being placed on drum | Lever being closed slowly |
Open and Closed Head Drums with Fittings
- Check Gasket: Inspect plugs for proper gasket seating.
- Install Plug: Do not cross thread.
- Tighten: Use specification listed below:
| Plug & Gasket Types |
Tri-Sure Buna |
Tri-Sure poly or teflon |
Reike (plastic) |
Reike (steel) poly |
Reike (steel) all other |
Nuc-Fil filters |
| 3/4" plug |
12 ft-lbs |
20 ft-lbs |
9 ft-lbs |
20 ft-lbs |
15 ft-lbs |
8-12 ft-lbs |
| 2" plug |
20 ft-lbs |
30 ft-lbs |
20 ft-lbs |
40 ft-lbs |
30 ft-lbs |
-- |
Note:Skolnik Industries can supply torque wrenches for plugs.
NOTES:
- Under the applicable DOT regulations, any changes made to the method of closure or closure components constitute a change in the design type of this packaging, and invalidate the embossed certification.
- After filling and prior to transport, the shipper should check the tightness of closures to determine if the effects of heating, cooling or gasket relaxation have resulted in the need to tighten the closure.
- Drums (other than the composites) are tested at room temperature.
|